YukonMontanaTannerTrapper
Explorer
Simultaneous to the house demolition / construction is the on-going site work. I have not written too much on that subject so far (at least that's what my brain tells me).....so this next post is all about site work (and I'll need to address at some point some of the other site work tasks that have been completed as well).....
May 13, 2021 (continued).....late that evening I'd say it was maybe 6:00 p.m. when the surveyor showed up to stakeout the proposed drainfield corners.....

It's absolutely amazing the way that the engineering field has changed over the past two decades.....the thought that one guy can come out here and do the work that previously took at least two people.....and often three.....

May 17,2021.....a few days later the "whiney baby" drainfield guy arrived.....that guy could barely get one foot out of his truck before he started complaining.....it took them two days to complete the installation.....he was still complaining when he put that last foot back into his truck and drove off into the beautiful Montana sunset.....

The drainfield installation process is really a simple one.....first you dig a trench from the house foundation to the proposed location of the septic tanks.....

For this particular build there were two tanks that needed to be installed.....each having a 1,000 gallon capacity.....the reason for such large storage is that the drainfield was designed for a 3 bedroom house.....not the 1 bedroom that we are actually building.....


Once the tanks were installed, the guys dug a trench to the actual drainfield which was maybe 100' feet away.....then three trenches were dug at a depth of ONLY 2' as the soil here is so rocky that it's not recommended to go any deeper.....

Once the drainfield pipes are in the ground, everything is backfilled.....and since that drainfield is so shallow in the ground, a two foot high mound of dirt covered it.....hopefully keeping it from freezing during those long, dark, cold winter months of Montana (which I don't plan to see).....


The total cost of that installation was $14,600 and if you add the surveyor, the preliminary design work, permits, and what not.....I'm guessing (& only guessing) that there's $20,000 in that drainfield.....I couldn't help but think composting toilet.....but then that's just how us Overlanders think.....

May 13, 2021 (continued).....late that evening I'd say it was maybe 6:00 p.m. when the surveyor showed up to stakeout the proposed drainfield corners.....

It's absolutely amazing the way that the engineering field has changed over the past two decades.....the thought that one guy can come out here and do the work that previously took at least two people.....and often three.....

May 17,2021.....a few days later the "whiney baby" drainfield guy arrived.....that guy could barely get one foot out of his truck before he started complaining.....it took them two days to complete the installation.....he was still complaining when he put that last foot back into his truck and drove off into the beautiful Montana sunset.....

The drainfield installation process is really a simple one.....first you dig a trench from the house foundation to the proposed location of the septic tanks.....

For this particular build there were two tanks that needed to be installed.....each having a 1,000 gallon capacity.....the reason for such large storage is that the drainfield was designed for a 3 bedroom house.....not the 1 bedroom that we are actually building.....


Once the tanks were installed, the guys dug a trench to the actual drainfield which was maybe 100' feet away.....then three trenches were dug at a depth of ONLY 2' as the soil here is so rocky that it's not recommended to go any deeper.....

Once the drainfield pipes are in the ground, everything is backfilled.....and since that drainfield is so shallow in the ground, a two foot high mound of dirt covered it.....hopefully keeping it from freezing during those long, dark, cold winter months of Montana (which I don't plan to see).....


The total cost of that installation was $14,600 and if you add the surveyor, the preliminary design work, permits, and what not.....I'm guessing (& only guessing) that there's $20,000 in that drainfield.....I couldn't help but think composting toilet.....but then that's just how us Overlanders think.....
